How We Build
 Our Philosophy
 A Freespan Model Home
 Expert Craftsmanship
A Typical Schedule
 Get a Construction Estimate
 Our Advantages
 Where We Build
 FAQ
 

Due to normal variations in the custom construction process including the ordering, manufacture and installation of your selections, the completion date may be forty-five days earlier or later than projected. Your final move in date will be determined approximately thirty days before the scheduled completion date.

While every effort will be made to accommodate you, there are the day-to-day uncertainties of conflicting schedules and subcontractor reliability. Unlike the routine steady pace of the manufacturing business, you will find the progress on your house to come in spurts, with periods of great activity and other times when it appears that nothing is happening. Often there are things happening which are not readily visible such as inspections, deliveries, or just a one or two day wait for someone to be available for a certain task. Historically our deliveries have been very close to schedule. As your home nears completion we will keep you informed as to the final delivery date..

PRE-CONSTRUCTION
0.1 Meet new clients
0.2 Prepare or redraw plans
0.3 Prepare estimate
0.4 Prepare draft contract/specifications
0.5 Review drawings
0.6 Prepare final cost estimate/contact and specs
0.7 Apply for electrical service
0.8 Submit building permit including site plan with septic information
0.9 Prepare to drill well and stake well location
0.10 Drill well

WEEK 1
1.1 House stakeout
1.2 Phone for clearing
1.3 Flag for clearing
1.4 Clear lot

WEEK 2
2.1 Order basement windows/doors
2.2 Phone for foundation excavation
2.3 Obtain building permit
2.4 Excavation layout
2.5 Phone for footings
2.6 Excavate foundation
2.7 Phone mason for block delivery
2.8 Deliver basement windows/doors

WEEK 3
3.1 Footings
3.2 Phone for roof trusses
3.3 Phone for footing inspection
3.4 Phone for structural steel/drain tile/columns
3.5 Nail points in footings
3.6 Phone for underslab plumbing/laterals
3.7 Phone for concrete slab work

WEEK 4
4.1 Deliver block
4.2 Start foundation walls
4.3 Phone for partial backfill
4.4 Phone carpenter
4.5 Phone for wall check survey
4.6 Order basement gravel

WEEK 5
5.1 Complete foundation walls
5.2 Phone for 1st floor lumber package
5.3 Deliver structural steel
5.4 Parge foundation walls

WEEK 6
6.1 Underslab plumbing
6.2 Wall check survey
6.3 Phone for parging inspection
6.4 Underslab plumbing inspection
6.5 Partial backfill

WEEK 7
7.1 Grade basement subgrade and gravel
7.2 Pour basement floor
7.3 Inspection for slab
7.4 Grade garage subgrade

WEEK 8
8.1 Dig and install W&S laterals or well and septic
8.2 Deliver steel framing package
8.3 Set structural steel
8.4 Pour garage slab

WEEK 9
9.1 Frame house
9.2 Grade crawl space

WEEK 10
10.1 Phone for windows and exterior doors
10.2 Finish Framing

WEEK 11
11.1 Phone for stair/rail measurement
11.2 Sheath house

WEEK 12
12.2 Phone for brick veneer

WEEK 13
13.1 Phone Utility re: URD cable
13.2 Order shingles
13.3 Finish sheathing

WEEK 14
14.1 Phone for plumbing rough-in
14.2 Phone for backfill and rough grade
14.3 Deliver windows and exterior doors
14.4 Phone heating and A/C rough-in

WEEK 15
15.1 Set windows and exterior doors
15.2 Deliver stairs
15.3 Backfill and rough-grade
15.4 Phone roofers
15.5 Phone for exterior trim package
15.6 Phone for exterior siding material

WEEK 16
16.1 Begin brick veneer
16.2 Set interior stairs
16.3 Phone for siding installers
16.4 Roofing

WEEK 17
17.1 Order hardware package
17.2 Plumbing rough-in
17.3 Phone for electric rough-in
17.4 Order hardwood flooring

WEEK 18
18.1 Prepare interior finish schedule/door order
18.2 Order kitchen cabinets and A/C rough-in
18.3 Heating and A/C rough in

WEEK 19
19.1 Interior framing backup inc. soffits/box ducts
19.2 Phone for garage door
19.3 Phone for exterior trim
19.4 Deliver exterior trim package
19.5 Electric rough-in
19.6 Begin exterior trim (cornice)
19.7 Phone for concrete steps
19.8 Phone for insulation
19.9 Phone for drywall delivery and installation
19.10 Install water meter
19.11 Install furnace
19.12 Complete exterior trim (cornice)
19.13 Obtain electrical/plumbing rough-in

WEEK 20
20.1 Call for framing inspection
20.2 Framing inspection
20.3 Hang garage doors
20.4 Form concrete steps
20.5 ABC framing inspection
20.6 Frame punch-out
20.7 Pour concrete steps

WEEK 21
21.1 Install insulation
21.2 Call for insulation inspection
21.3 Order light fixtures
21.4 Phone for interior door and trim package
21.5 Insulation inspection
21.6 Deliver Drywall
21.7 Install electric meter
21.8 Phone for gutters and downspouts
21.9 Phone for drywall hanging

WEEK 22
22.1 Turn on heat
22.2 Hang and tape drywall
22.3 Phone for driveway
22.4 Phone for exterior painting
22.5 Order ceramic tile
22.6 Hang gutters and downspouts
22.7 Exterior painting
22.8 Phone kitchen cabinet/vanities delivery

WEEK 23
23.1 1st coat drywall
23.2 Phone for final grading
23.3 Phone for rail delivery
23.4 Order kitchen appliances
23.5 Last date for paint selection
23.6 Deliver wood flooring
23.7 Lay wood floors

WEEK 24
24.1 Deliver interior doors and interior trim
24.2 Interior trim
24.3 Final grade by excavator
24.4 Deliver kitchen cabinets & vanities

WEEK 25
25.1 Install kitchen cabinets and vanities
25.2 Measure/order countertops
25.3 Phone for seeding or sodding
25.5 Install ceramic tile
25.6 Phone for switch and plug
25.7 Phone interior paint/caulk
25.8 Deliver hardware package

WEEK 26
26.1 Prime paint
26.2 Drywall point-up/sand
26.3 Fine grade yard for seed
26.4 Phone for final HVAC
26.5 Phone floor finishing

WEEK 27
27.1 Deliver countertops
27.2 Set countertops
27.3 Deliver kitchen appliances
27.4 Sand and finish floors
27.5 Phone final survey
27.5 Paper hardwood floors

WEEK 28
28.1 Deliver electrical fixtures
28.2 Hang electrical fixtures
28.3 Final HVAC startup/grills
28.4 Set plumbing fixtures
28.5 Set Kitchen appliances

WEEK 29
29.1 Call for water test
29.2 Lay carpet/vinyl
29.3 Call for final clean
29.4 Hang electrical fixtures
29.5 Final survey
29.6 Phone for A/C or heat check
29.7 Set finish hardware
29.8 Hang mirrors

WEEK 30
30.1 Hang window screens/grills
30.2 Phone for final clean
30.3 Install shoe mold
30.4 Final clean
30.5 Walk-thru with client
30.6 Call for final inspection
30.7 Final inspection
30.8 Issue final occupancy permit

 





Freespan Homes » 2919 East Hardies Road » Gibsonia, PA 15044 » 1-888-466-5803


Privacy Policy     Site Terms of Use